In the Pending Changes view, you can integrate outgoing
changes by performing a deliver operation.
Procedure
To integrate outgoing changes:
- Open the Pending Changes view. In the ClearTeam Navigator,
select the ClearCase view in which you want accept incoming changes.
Right-click the view and select from the context menu in the ClearCase
Navigator or click the Show Pending Changes icon
on
the ClearCase toolbar.
- In the Pending Changes view, click on the Integrate
All Outgoing Changes icon
on the Pending Changes view toolbar.
- If this is the first time that you have selected this option
for the current view, the Default Deliver Configuration dialog
box displays. Ensure that the target stream and the integration view
are correct and click OK. Note that
you can also specify these options in the preferences.
- The Ready to Complete Deliver dialog
box appears. Specify whether to leave the deliver operation in its
current state, complete the deliver operation, or cancel the deliver
operation. and click OK.
- If you chose to complete the deliver operation, click OK in
the Rebase confirmation dialog box. The
Pending Changes view now shows no outgoing changes.
- To enable others to access the changes you have delivered,
make a new baseline by navigating to the integration stream, right-clicking
the stream name, and selecting Make Baseline,
specify the options you want and clicking OK.