(→HA Configuration)
|
| Line 3: | |||
| The following activities should be performed in the order presented. | The following activities should be performed in the order presented. | ||
| - | 1. Provision the uDeploy Server Machines | + | 1. Provision the uDeploy Server Machines in preparation for the next step |
| 2. Install and Configure Load-Balancer: The LB should forward to the machine provisioned in step 1. | 2. Install and Configure Load-Balancer: The LB should forward to the machine provisioned in step 1. | ||