You can establish a test schedule by associating a test
plan with iterations from a project area or team area timeline. You
can also list key project dates, such as the date of the final release,
code freeze, UI freeze, beta entry, or beta exit.
Before you begin
Test plan schedules are defined as iterations and timelines
in the Jazz™ process, and as
a result, test plan authors must have permission to create and modify
iterations. This permission is applied at the Project Configuration
level. You can find this permission in the Process section of Permitted
Actions. The specific permission that is required is named
"Modify
the iteration structure". Optionally, you can create a test plan
author role and assign this permission to that role. Otherwise, all
of the Process permissions are enabled for the Test Team Member role
by default.
About this task
If a team area is associated with a particular timeline,
you can select the team area in the test plan and associate the test
plan schedule with the iterations in that timeline. For more information,
see Timelines
and Iterations® in Rational® Quality Manager.
Note: In
the Quality Management application, you must explicitly enable the
use of team areas and multiple timelines.
Procedure
- Open a test plan.
If team areas are enabled
and a team area is associated with a timeline, you can associate the
test plan with a team area by selecting a team area from the list.

- Open the Test Schedules section
of the test plan.
- Click Browse.
- In the Browse window, select an iteration and click OK.
The test schedule is populated with the selected iteration
and its child iterations as shown in the following image:
Tip: To get multiple iterations in the test
schedule, you must define a hierarchy of iterations. In the previous
example, the top-level iteration (4.0) represents a release and the
child iterations (M1, M2, and so on) represent iterations or milestones
within the release.
- When the iterations are displayed in the test schedule,
select an iteration, and in the Actions column, click the Edit (
) icon. The Edit Properties window
opens as shown in the following image:

Note: The planned start and end dates
are inherited from the dates in the timeline, as are the actual dates
that are shown in brackets next to the iteration name. Initially,
the planned dates and actual dates are identical. To update the actual
dates, use the timeline editor. When you make updates in the timeline
editor, the new dates are reflected in the iteration name. The planned
dates do not change. If you need to change the planned dates, make
that change in the test schedule, not the timeline editor.

- Provide the detailed iteration properties.
- In the Description field, type
a description for the iteration.
- In the Points field, type a points
value, which is an estimate of the execution effort for the iteration. Alternatively, you can provide more detailed information about
the distribution of these points over time in the Plan Details window.
See step 7.
- In the Planned Defects field,
type the number of projected defects.
- In the Defect Validity Rate field,
type the number of defects that are determined valid.
- If necessary, click the planned start date and use the
calendar to select the date.
Note: If you did not initially
supply a planned end date, supply one now.
- Click OK to save the iteration
properties.
- Repeat for each iteration in the schedule.
- Click Save to save the schedule.
- Optional: You can click the Plan Details (
) icon to estimate the work to be done and distribute
points over the iteration. The plan details are reflected in the Planned
Attempted and Planned Complete points on the Execution Trend report.
Point estimates that you enter in this window will override the points
value that you previously provided for the iteration. - To automatically distribute points over an iteration, click
the Auto Generation icon.
- To manually distribute points over an iteration, Click the Add
Row (
) icon, and type the estimated values for the date,
the points to be attempted by that date, and the points to be completed
by that date. Add new rows for each date, and then click OK.
- List key project dates:
- Click the Add Key Dates icon
(
) to add a date that you want to track in the test
plan.
- Repeat the previous step for each date to include.
- Click Save to save the schedule.
- Update the dates as needed as the project evolves.