Checking project status with the Execution Trend Report

You can use the Execution Trend report to find out if your project is on schedule.

Execution Trend

This report estimates the actual test execution progress against the planned progress. Weight is used to determine how much work is complete, how much work is left, and whether progress is being made as expected. The graph is based on the following data:
  • Weight: The total weight used in this report is equal to the sum of all weights of the test case execution records in a test plan.
  • Days: The dates used in this report are derived from the actual start and end dates of the test schedules of the test plan.
Important: To generate the report, you must have these dates defined. If you do not know the actual dates yet, use the same dates that you defined for the planned start and end dates. You can later update the fields with the actual dates.

You define these dates in the Test Schedules section of the test plan. All of the points between these dates are programmatically determined based on the time interval that you choose in the Chart Grouping parameter for the report.

Test Schedule section of a test plan

You can estimate the work that will get done from the Plan Details window. To view the details for a specific iteration, point at the Actions column; then click the Plan Details (Plan details icon) icon. The values in the Plan Details table are used to plot the following lines on the Execution Trend report:
  • The values in the Points attempted column = the points on the graph for the Planned Attempted line.
  • The values in the Points completed column = the points on the graph for the Planned Completed line.
  • The last value in the Points attempted column is used to determine the points on the graph for the Computed Attempted line.
  • The last value in the Points completed column is used to determine the points on the graph for the Computed Complete line.
Here is an example of how you might set up the Plan Details. Notice that work is estimated to get done in increments:
Plan Details window in the Test Schedule section
To run the Execution Trend report:
  1. Click Reports > Shared Reports.
  2. Under the Execution section, click Execution Trend.
  3. Select your parameters, and click Run.

Here is an example of the Execution Trend Report:

Execution Trend Preview

The chart graphs the following information:
  • Complete: Plots the combined weight of completed test case execution records that match the selected parameters.
  • Attempted: Plots the combined weight of attempted test case execution records that match the selected parameters.
  • Computed Complete: Uses the total number of points from the Points completed column in the Plan Details of the Test Schedule section to plot expected progress based on a standard s-curve.
  • Computed Attempted: Uses the total number of points from the Points attempted column in the Plan Details of the Test Schedule section to plot expected progress based on a standard s-curve.
  • Planned Complete: Plots the Points completed from the Plan Details of the Test Schedule section.
  • Planned Attempted: Plots the Points attempted from the Plan Details of the Test Schedule section.
Tip: To ensure that your graph displays accurate information about how iterations are progressing, make sure that you set a iteration in each test case execution record. In addition, make sure that you run the data collection jobs to see any updated data. You can set the time interval for automatically running the data collection jobs from the Reports page of the Server Administration application.


Have a problem or a question? Post it in the Jazz.net forum.