Project Management Orientation
7. Start-to-start precedence relationships __________.
Include one or more key activities that must be started at the same time so that a project can remain on schedule
Require that a predecessor activity be completed before the successor activity is scheduled to finish
Finish one activity before another activity begins
All of the above
SUBMIT
1: Getting Started
2: Define the Project Team
3: Team Management
4: Identify and Validate Requirements
5: Create Decomposition Structures
6: Risk Management
7: Project Estimates
8: Project Schedules
9: Change Management
10: Project Control and Execution
11: Project Management Review
12: Project Closeout
13: Project Management Tool Suite
14: Self-Assessment and Final Exam
Fast Points
Concepts
Seven Keys
Case Study
WWPMM
Mentor
Check Point